Kamoa-Kakula’s 3 November operating update links copper throughput to smelter feed and power availability.

Ivanhoe Mines · 2026-11-03

Kamoa-Kakula lowers 2027 copper guidance as its smelter runs at about 60% of capacity

Ivanhoe Mines said on 3 November that Kamoa-Kakula in DR Congo had lowered its 2027 guidance to 300,000–350,000 tonnes of copper in saleable products. Its existing smelter continues to operate at about 60% of design capacity, according to the company.